Word salad stymies lagoon build in Swansea

07 December 2022
Issue: 8006 / Categories: Legal News , Construction , Environment , Property
printer mail-detail
Mixing up the words ‘begin’ and ‘commence’ is ‘imprecise’ and cannot be condoned, yet such ‘loose language’ is not enough to create separate time limits for work on the proposed Swansea Bay tidal energy lagoon, the Court of Appeal has held.

A dispute arose between the Welsh authorities and the company proposing to build the £1.3bn renewable energy project over deadlines in the development consent order (DCO).

In Tidal Lagoon (Swansea Bay) plc v Secretary of State for Business, Energy and Industrial Strategy and others [2022] EWCA Civ 1579, the court considered the difference between ‘begin’ and ‘commence’—under the DCO, the authorised development was to ‘commence no later than the expiration of five years…’. The company argued that this requirement could not be construed as replacing the time period under the Planning Act 2008, which provided a five-year period for the development to be ‘begun’. It contended this meant two separate time periods had been set, which meant the DCO was still in force and therefore the company could apply for an extension.

The Welsh authorities, however, successfully countered that this approach was ‘dysfunctional and contrary to the clear intention of the legislation’.

Dismissing the company’s appeal, Sir Geoffrey Vos, Master of the Rolls, Sir Keith Lindblom, Senior President of Tribunals, and Lord Justice Stuart-Smith said: ‘We were initially attracted by the company's argument that… it must have been intended to create two different time periods: one to decide when the DCO lapsed under [the 2008 Act] and the other to decide the time by which the development had been commenced.

‘Ultimately, however, we concluded that this argument proves too much… The consequences of the construction proposed by the company would be undesirable. DCOs could be left on the stocks for years, inhibiting future development and placing landowners at potential risk of delayed compulsory purchases.’

Issue: 8006 / Categories: Legal News , Construction , Environment , Property
printer mail-details

MOVERS & SHAKERS

Muckle LLP—Rachael Chapman

Muckle LLP—Rachael Chapman

Sports, education and charities practice welcomes senior associate

Ellisons—Carla Jones

Ellisons—Carla Jones

Partner and head of commercial litigation joins in Chelmsford

Freeths—Louise Mahon

Freeths—Louise Mahon

Firm strengthens Glasgow corporate practice with partner hire

NEWS
One in five in-house lawyers suffer ‘high’ or ‘severe’ work-related stress, according to a report by global legal body, the Association of Corporate Counsel (ACC)
The Legal Ombudsman’s (LeO’s) plea for a budget increase has been rejected by the Law Society and accepted only ‘with reluctance’ by conveyancers
Overcrowded prisons, mental health hospitals and immigration centres are failing to meet international and domestic human rights standards, the National Preventive Mechanism (NPM) has warned
Two speedier and more streamlined qualification routes have been launched for probate and conveyancing professionals
Workplace stress was a contributing factor in almost one in eight cases before the employment tribunal last year, indicating its endemic grip on the UK workplace
back-to-top-scroll