Word salad stymies lagoon build in Swansea

Mixing up the words ‘begin’ and ‘commence’ is ‘imprecise’ and cannot be condoned, yet such ‘loose language’ is not enough to create separate time limits for work on the proposed Swansea Bay tidal energy lagoon, the Court of Appeal has held.

A dispute arose between the Welsh authorities and the company proposing to build the £1.3bn renewable energy project over deadlines in the development consent order (DCO).

In Tidal Lagoon (Swansea Bay) plc v Secretary of State for Business, Energy and Industrial Strategy and others [2022] EWCA Civ 1579, the court considered the difference between ‘begin’ and ‘commence’—under the DCO, the authorised development was to ‘commence no later than the expiration of five years…’. The company argued that this requirement could not be construed as replacing the time period under the Planning Act 2008, which provided a five-year period for the development to be ‘begun’. It contended this meant two separate time periods had been set, which meant the DCO was still in force and therefore the company could apply for an extension.

The Welsh authorities, however, successfully countered that this approach was ‘dysfunctional and contrary to the clear intention of the legislation’.

Dismissing the company’s appeal, Sir Geoffrey Vos, Master of the Rolls, Sir Keith Lindblom, Senior President of Tribunals, and Lord Justice Stuart-Smith said: ‘We were initially attracted by the company's argument that… it must have been intended to create two different time periods: one to decide when the DCO lapsed under [the 2008 Act] and the other to decide the time by which the development had been commenced.

‘Ultimately, however, we concluded that this argument proves too much… The consequences of the construction proposed by the company would be undesirable. DCOs could be left on the stocks for years, inhibiting future development and placing landowners at potential risk of delayed compulsory purchases.’

Issue: 8006 / Categories: Legal News , Construction , Environment , Property
printer mail-details

MOVERS & SHAKERS

Thackray Williams—Lucy Zhu

Thackray Williams—Lucy Zhu

Dual-qualified partner joins as head of commercial property department

Morgan Lewis—David A. McManus

Morgan Lewis—David A. McManus

Firm announces appointment of next chair

Burges Salmon—Rebecca Wilsker

Burges Salmon—Rebecca Wilsker

Director joins corporate team from the US

NEWS
What safeguards apply when trust corporations are appointed as deputy by the Court of Protection? 
Disputing parties are expected to take part in alternative dispute resolution (ADR), where this is suitable for their case. At what point, however, does refusing to participate cross the threshold of ‘unreasonable’ and attract adverse costs consequences?
When it comes to free legal advice, demand massively outweighs supply. 'Millions of people are excluded from access to justice as they don’t have anywhere to turn for free advice—or don’t know that they can ask for help,' Bhavini Bhatt, development director at the Access to Justice Foundation, writes in this week's NLJ
When an ex-couple is deciding who gets what in the divorce or civil partnership dissolution, when is it appropriate for a third party to intervene? David Burrows, NLJ columnist and solicitor advocate, considers this thorny issue in this week’s NLJ
NLJ's latest Charities Appeals Supplement has been published in this week’s issue
back-to-top-scroll